Forth Ports – Grangemouth

F2 clear span portal storage facilities.

This was a fast construction programme with the first building comprising of 45m clear span portal, completed including roof and wall cladding envelope within 6 weeks from commencing on site utilising our own site plant.

  • 1,030t Structural Steel

Ultimate Client:
Forth Ports

Main Contractor:
Luddon Construction Ltd

Structural Engineer:
IKM/Ramage Young

Architect:
TBC